Please see the AIP, it should serve your purpose once implemented: What you can currently do is to use branch operator and do: Run this daily and it should work as expected. |
2 replies
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
Uh oh!
There was an error while loading. Please reload this page.
So I found where the L can be used to indicate the last day of the month. I have taken a couple shots at scheduling the last three days of the month with no success. I have only been working with airflow a month or so. Is this something someone knows how to do, or is this too difficult to implement? I tried putting the following:
But since a dash means an interval (instead of subtracting the number of days) it would not work. Any ideas would be appreciated.